Skip to main content

Procedure Pump Installation

.  Installation

 

 

1.1. Installation of common baseplate

 

Installation   and  centering  of  the  pump  should  be  performed  by  skilled  workers.  Improper  installation  and centering would cause various troubles during the pump running. When the pump and its driver are shipped as directly coupled  on the common  baseplate,  they have already  been  leveled  and centered  completely  at our fabrication  shop before shipment.

However, install the common baseplate (with pump and driver properly in the sequence given below and recheck the level and centering of pump and its driver).

(1)   Prepare packers (steel wedges) and several kinds of 1 mm ~ 0.1 mm thick levelling shims.

 

(2)   After complete cure-up of the pump foundation, place and position packers on the foundation at the both sides of  each  anchor  bolt  seat  so that  the common  bed  can  be put  on the packers  later  on.  Thereafter,  grout concrete  on  the  foundation  floor  at  each  packer  position  and  re-place  and  reposition  the  packers  on  the concrete.  In this case,  don't fail to keep  each packer  right  horizontal  after  adjusted  by  use of a level.  The height of each packer is to be fine-adjusted  by insertion of shim(s) when the common bed is installed thereon. Accordingly,  at this stage only horizontality adjustment of the packers is sufficient.

(3)   After complete cure-up of the concrete with packer on, temporarily  install the common baseplate (with pump and driver)  on the packers  and check  the center  height  of the pump.  Furthermore,  hold a level on the dis - charge  flange  to make fine-adjustment  of the  pump  horizontality  in both  axial  and  crosswise  directions  by inserting previously prepared levelling shims between the baseplate and each packer.

(4)   After  the pump  was  positioned  and  levelled,  make  pre-center  alignment  between  the pump  and the driver using a centering jig (refer to 1.2 for the detail). In this case, recording the numeral date on pre-alignment  will be helpful when the direct coupled condition is checked.

(5)   After pre-centering,  grout concrete in each anchor bolt holder.

 

(6)   After  complete  cure-up  of  the  concrete  in  each  anchor  hole,  tighten  each  anchor  bolt  nut  with  unifor m tightening  torque.  In this case, check  and readjust  the center  alignment  between  coupling  halves,  based on the recorded numeral pre-alignment  data.

(7)   After the above check, grout mortar under the common bed till it reach es entirely all the corners of the bed s o that no cavity exists under the bed.

(8)   After completion  of all the above items, connect the suction pipe and discharge pipe to the respective flanges of the pump

 

 

1.2. Direct Coupling

The  pump  shaft  and  the driver  shaft  must  be centered  in line.  Therefore,  make  centering  in the  following procedure without fail.

(1)   For centering  of the coupling,  put a straightedge  on the both coupling halves and insert a wedge gauge in the axial clearance  between  the coupling  halves,  as  illustrated  in Fig.  2, to check  run-out  of the coupled shafts.

. 

  


(2)   In this case, measure the concentricity  and parallelism  of the coupling halves (the both shafts) respectively  at

 

4 points spaced at 90. The specified accuracy shall be within 0.1 mm respectively.

 

(3)   Check the drivers  rotating  direction  without  fail, before  connecting  one coupling  half (pump side) and other coupling half (driver side) together. The correct rotating direction  of the pump is shown with an arrow mark on the side face of the bearing pedestal, that is, clockwise direction viewing from the driver side.

(4)   If the rotating direction is correct, connect two coupling halves together.

 

(5)   Further, if the temperature  of pumping liquid exceeds the normal temperature range of changes widely during pump running, the direct coupling  will possibly deviate a little. In such case, therefore,  use the coupling with large flexibility.

 

 

1.3. Piping

 

After  completion  of  the  direct  coupling  work,  the  suction  and  discharge  pipes  must  be  connected  to  the respective flanges of the pump. Perform the piping connection with good care for the following items.

(1)   When connecting the suction and discharge pipes, take proper measure to prevent piping load from directly acting on the pump. Direct load to the pump by piping would cause trouble.

(2)   The suction line must be installed in upward slope (about 1/50) toward the pump prevent air leak and air pocket in the case of suction lift. And it must be installed in downward slope reversely in the case of forced suction.

(3)   Take to minimize various losses of the suction pipe and avoid sudden changes of cross -section and use of abrupt bends in the suction piping. Select the pipe size such that the flow velocity in the pipe does not exceed 3 m/s.

(4)   When the suction pipe size is different from the pump suction nozzle size, use an eccentric tapered pipe to connect

 

 

 

 

(5)   When  a sluice valve  is installed  on the discharge  line,  located  the valve  as close  as possible  to the discharge nozzle of the pump. Further, when a check valve and a sluice valve are provided  o the discharge line, locate the check valve between the pump discharge nozzle and the sluice valve.

(6)   In case of starting operation of a plant for the first time, various foreign matters remain in its pipe line and may

possibly flow into the pump. In such case, therefore, provide a strainer on the suction line for complete removal of foreign matters. The strainer used shall have the passing area equal to 3 ~ 4 times the sectional area of the suction pipe. If the strainer is clogged with foreign matters during the pump running, readings of the suction line pressure gauge will fluctuate. Sometimes, clean the strainer to remove foreign matters.

(7)   When external flushing water piping is provided, clean adequately the flushing water pipe before connecting.

(8)   The temperature of pumping liquid significantly different from the atmospheric temperature would cause the pipe line to shrink or expand. In such case, install a flexible pipe, etc. on the pipe line to prevent the load by shrink age o the pump.

(9)   After completion of the piping work, recheck that the pump is free from abnormal load by piping as well as free from alignment deviation, and make re-adjustment when required upon rechecking.

2. Operation

 

2.1. Starting

 

(1)   Before  starting  the  initial  operation  after  installation,  observed  the  following  check  items  and,  if  anything abnormal is found, take necessary corrective action in accordance with this manual.

 

(1)  Are the pump and the suction pipe filled up with pumping liquid ?

 

(2)   Is the driver's rotating direction correct ? (Pump rotates clockwise viewing from the driver's side) (3)   No abnormal in the direct coupling ?

(4)   No abnormal load to the pump by piping ?

(5)   Is the flushing pipe connected properly and the water flow rate proper ? (6)   Are the suction valve fully opened and the discharge valve fully closed ?

 

(7)   Isnt the gland packing tightened irregular or too excessively? Also, isnt there any abnormal leakage

 

from the gland packing ?

 

(8)  Can the pump be turned lightly by hand ?  Isnt there any t ouch of contact in the pump ?

 

(2)    If  nothing  abnormal  is  found  upon  checking  the  above  items,  turn  on  the  drivers  start  switch  and  of  it immediately to check that the pump rotates smoothly and shut downs quietly.

(3)   If normal rotation  of the pump is confirmed,  gradually  open the discharge  valve up to the specified  running speed. W hen leakage from the gland is much, re-tighten the gland packing with equal torque for adjustment

 

(4)   If the pump continues running with the discharge valve fully closed, the liquid temperature in the pump will rise, causing trouble of the pump. In such case, shut down the pump immediately without fail.

(5)   W hen starting the pump after long term shut down, recheck the above check items (1), and (5) then (8) to verify that the pump is abnormal-free.

 

2.2. Shutdown

 

Follow the procedure given below for shutting down the pump.

 

(1)   Gradually  close  the  discharge  sluice  valve  up  to  full  close  position.  However,  it  may  be  left  as  opened providing that a check valve is included in the discharge pipe and the back pressure is sufficient.

(2)   Turn of the driver s stop switch. At the same time, check that the pump rotational speed declarat ion smoothly and stops quietly.

(3)   Stop external flushing, if any.

 

(4)   Fully close the suction valve when the pump is kept as shutdown for long time.

 

(5)   When there is a possibility  of freezing  in the pump, completely  drain out the pumping  liquid from the volute casing. (Complete drain of the liquid in the line is more safety).

 

2.3. Operation and Maintenance

 

2. 3. 1. General

 

The pump must run quietly without abnormal vibration all the times. Therefore, carefully observe the following check items while the pump is in running and, if anything abnormal is found, shut down the pump imm ediately and search the cause.

(1)   Does the suction pressure fully satisfy the pump required NPSH (NPSH req.) ? (2)   Is the specified discharge pressure satisfied ?

(3)   Isnt the driver in overload running ?

(4)   Are the both suction pipe and volute casing filled up with pumping liquid and the discharge valve f ully opened in the pump running ?

(5)   Is the bearing temperature normal ? (no abnormal temperature rise ?)


(6)   Is leakage from the gland proper ?

 

(7)   Is the pump running with no abnormal noise and no vibration ?

2.3.2. Shaft seal

 

The shaft seal is available in two different types of gland packing and mechanical seal. The descriptions here under covers the gland packing seal type. Refer to Chapter IV for the detailed instructions of the mechanical seal.

The gland packing insertion  space in the casing cover  is designed  to be equivalent  the either five packing rings

 

(4610) or three packing rings plus one lantern ring (4580).

 

The gland bush (4540) is of split type as to facilitate insertion of the packing rings. (1)   Gland packing without lantern ring

The seal type is applied to the suction pressure of 0,5 kgf / cm2G and over or the handling of odorous liquids (e.g. ammonia  water  and benzine,  benzol or lubricant  for outdoor  use, etc.). In such cases, self flushing  or external flushing is not applied to the gland packing.

(2)   Gland packing with lantern ring

This seal type is applied to the following cases.

o     Clean liquid under suction pressure of 0.5 kgf/cm2G or under suction lift.

 

o     Pumping the liquid from vacuum tank.

o     The pump shaft  and its gland packing  must be protected  from  abrasion  for handling  liquid containing abrasive component, (e.g. handling of sewage and the like).

In such cases,  either  self flushing  or external  flushing  by proper  liquid is applied  to the gland packing  as des cribed below.

(a)   Self-flushing

In this case, flushing liquid is conducted into the lantern ring through a passage provided in the casing cover.

 

(b)   External flushing

This flushing system is applied to such case that inclusion of external liquid in the pumping liquid is allowed. In this case, same of the flushing liquid flows into the volute casing and the remaining is discharged  into the atmosphere through the clearance in the gland bush.

In the case of the gland packing shaft seal, packing  ring (4610),  lantern ring (4580)  and gland bush (4540)  ar e inserted in the stuffing box. In this case, the outside surface of shaft protecting  sleeve (5240) must keep smooth all the times.

Any flaw  on the shaft  protecting  sleeve  surface  or irregular  tightening  and  over -tightening  of the  gland  (4520)

would cause the shaft seal to be overheated and the packing rings to deteriorate earlier  than expected.

 

When the packing  rings  are replaced  with new ones,  packing  material  highly resistant  to pumping  liquid  and its temperature  must be used.  Before replacement,  clean the lantern ring, gland bush and gland and, cut the packing material to the specified dimension  with a proper cutter using the cutting jig illustrated in Fig. 4. Thereafter,  insert the packing rings, one by one into the stuffing box so that the butt ends of each ring are offset by 90° from each other on

the shaft protecting sleeve. (Refer to Fig. 5.)

 

 

 

 

 

 

 


Comments

Popular posts from this blog

PENGUJIAN ROUGNESS (KEKASARAN PERMUKAAN)

https://youtu.be/swx7DZEnM-U <![endif]--> TEORI DASAR PENGUJIAN ROUGNESS 3.1       Teori Dasar             Permukaan suatu benda kerja dari hasil pengerjaan mesin maupun yang lainya tentu akan mempunyai kekasaran pada permukaan benda tersebut, baik yang bergelombang maupun yang rata. Diantaranya faktor-faktor susunan permukaan benda tersebut adalah halus atau kasar permukaannya. Kekasaran permukaan benda kerja bukan disebabkan oleh permukaan yang bergelombang. Gambar 3.1 Garafik Gelombang Kerataan             Kurva kekasaran ditunjukan sebagai Y = F(x) dengan panjang kurva 1m, dimana garis sumbu kurva kekasaran permukaan benda sebagai sumbu x dan pembesaran arah vertikal sebagai sumbu y, Harga kekasaran (Ra) dapat dihitung dengan rumus :           ...

PROSES PENCEGAHAN KOROSI PADA PIPA DIBAWAH LAUT

PROSES PENCEGAHAN PIPA DARI KOROSI Coating pipa banyak jenis dan macamnya. Diantaranya yaitu: Three Layer Pholyethilen, Three layer polypropylene, FBE powder Coating, Cement Lining, Coating Coltar, Varnish, Galvanis, Coating Tape dan Epoxy seperti yang telah dibahas pada Bab tiga. Pada projek ichthys ini proses pengaplikasian coating menggunakan metode Multi layer polypropylene sehingga kekuatan dan fungsinya sesuai dengan yang diharapkan oleh client. Fungsi utama dari proses pengaplikasian ini adalah untuk mencegah terjadinya korosi dan mencegah terbentuknya Hidrat sebagai mana yang telah dijelaskan pada bab tiga. 1. MLPP Champer             MLPP Champe merupakan permukaan yang harus diperhatikan agar kemiringan dari MLPP dasar tidak kurang dari 3 0 dengan toleransi +5 0 . fungsi dari pembuatan champer ini agar saat   proses IMPP tidak terjadi disbonment . Sehingga   kualitas dan kerekatan ( bondit ) pada saat pengap...